Pontchaillou Hospital

New technical equipment was installed in the hospital, requiring a new opening to route various power cables.

On this page

Topic
Reinforcement slab opening
Object
Pontchaillou Hospital
City
Rennes
State
Ille-et-Vilaine
Country
France
Date
Duration
1 Day

Problem

The concrete floor had to be cut, resulting in the severing of the reinforcement and a loss of structural continuity.

Solution

As the opening was located directly in line with the load-bearing beam, the S&P C‑Laminate carbon NSM (near-surface mounted) solution was designed to minimise the impact on the future use of the room. As the laminates are embedded within the concrete, no additional mechanical protection is required.

Material

20 m S&P C-Laminate 10/2,8 & 6kg S&P Resin 55 HP

Contact

S&P Clever Reinforcement Switzerland

S&P Clever Reinforcement Company AG Headquarters

Seewernstrasse 127
6423 Seewen
Switzerland