Situation
In January 2022, our application engineers were invited to install 72 pieces of pre-stressed carbon laminates (S&P C-Laminate) together with a contractor. Beforehand, the S&P engineering department assisted with the planning of the entire project. The commercial building is located in the middle of the city of Zug and is currently undergoing a complete renovation.
In addition to the pre-stressed FRP laminates, the project also included numerous standard surface bonded laminates. In total 600 metres of S&P C-laminate and 480 kg of S&P Resin 220 HP epoxy resin were used, as well as S&P Resin 55 HP being used as a bonding agent.